Kindred Terminal project updates

Project overview

The Kindred Terminal project will replace end-of-life grain storage and receiving assets, which should improve facility reliability and speed. Receiving speed will be increased by 10,000 bushels per hour while loadout speed will increase by 20,000 bushels per hour. Load time for shuttle trains is expected to decrease by six hours. The goal of the project is to improve speed, space and efficiency at the Kindred Terminal location.

Project updates


February 25, 2026, Kindred highlights

Great day for CHS! The first cement trucks have arrived on site in Kindred. Once they start pouring cement it will be continuous for 24 hours a day. The slip elevator pour will take approximately seven days.

February 11, 2026, Kindred highlights

Construction progress continues with the Kindred elevator project. The receiving building is taking shape and electrical equipment is being installed in the MCC building. The slip forms are in the final stages of completion; they are being enclosed so they can be heated during the construction.

Kindred project update February 11

February 5, 2026, Kindred highlights

Kindred elevator construction continues. The slip forms are being enclosed in plastic; the deck area will be heated during construction.

Kindred project update February 5th, 2026
Gwinner is now accepting corn and soybeans.